News

Episode 3: When the Entire Political System Moves in Unison

Hoang Sa - Chinh Thanh 07/05/2026 12:44

As the first construction fronts are deployed on the ground and public consensus continues to strengthen, the Tan Phu – Bao Loc and Bao Loc – Lien Khuong expressway projects are entering a critical phase.

Sơ đồ tuyến cao tốc Tân Phú - Bảo Lộc và Bảo Lộc - Tân Phú
Alignment map of the Tan Phu – Bao Loc and Bao Loc – Lien Khuong expressways.

At this stage, the key issue is no longer whether to implement, but how to organize execution—where each administrative decision can either accelerate or delay overall progress.

Ủy viên Ban Chấp hành Trung ương Đảng, Bí thư Tỉnh ủy, Trưởng Đoàn ĐBQH tỉnh Lâm Đồng Y Thanh Hà Niê Kđăm đề nghị thống nhất ý chí, tăng cường công tác phối hợp giữa các ban, ngành để các dự án trọng điểm triển khai đúng kế hoạch, phát huy hiệu quả (ảnh Lê Phước)
Member of the Party Central Committee, Secretary of the Lam Dong Provincial Party Committee and Head of the Lam Dong Provincial Delegation of National Assembly Deputies, Y Thanh Ha Nie Kdam called for unified resolve and stronger coordination among departments and agencies to ensure key projects are implemented on schedule and deliver effective results. Photo: Le Phuoc

Strong and Decisive Leadership

At the March 2026 Steering Committee meeting on key provincial projects and site clearance for the high-speed railway, Lam Dong Provincial Party Secretary Y Thanh Ha Nie Kdam emphasized: “Authorities at all levels must clearly define responsibilities, operationalize the principle of ‘local decision, local implementation, local accountability,’ and avoid delays caused by subjective factors.

cac-tuyen-cao-toc-tan-phu-bao-loc-va-bao-loc-lien-khuong-deu-da-duoc-khoi-cong-trong-nam-2025-1-.jpg
The Tan Phu – Bao Loc and Bao Loc – Lien Khuong expressway projects were both launched in 2025.

In practice, the entire political system has been mobilized. From provincial to grassroots levels, bottlenecks are being addressed through concrete, measurable actions tied to specific milestones.

Đồng chí Y Thanh Hà Niê Kđăm, Ủy viên Ban Chấp hành Trung ương Đảng, Bí thư Tỉnh ủy, Trưởng Đoàn ĐBQH khóa XV tỉnh Lâm Đồng chủ trì Hội nghị Ban Chỉ đạo thực hiện công trình, dự án trọng điểm của tỉnh và giải phóng mặt bằng dự án trọng điểm (ảnh Lê Phước)
Central Committee Member, Lam Dong Provincial Party Secretary and Head of the 15th National Assembly Deputies’ Delegation Y Thanh Ha Nie Kdam chairs the Steering Committee meeting on key provincial projects and site clearance for major projects. Photo: Le Phuoc

Chairman of the Provincial People’s Committee Ho Van Muoi has directed agencies to maximize remaining time, immediately implement feasible tasks, prioritize large-scale projects—especially expressways—and avoid repeating past shortcomings in public investment disbursement.

Ủy viên Ban Chấp hành Trung ương Đảng, Phó Bí thư Tỉnh ủy, Chủ tịch UBND tỉnh Hồ Văn Mười yêu cầu các Phó Chủ tịch UBND tỉnh, Bí thư các xã, phường, đặc khu “bắt mạch” từng dự án (ảnh Nguyễn Lương)
Central Committee Member, Deputy Secretary of the Provincial Party Committee and Chairman of the Lam Dong Provincial People’s Committee Ho Van Muoi instructs vice chairpersons and local Party secretaries at commune and ward levels to closely monitor and grasp the progress of each project. Photo: Nguyen Luong

For the Tan Phu – Bao Loc section, local authorities and land development agencies have been tasked with intensifying efforts, ensuring site clearance is completed on schedule. Provincial leaders have also been assigned to maintain an on-site presence to resolve issues in real time.

dong-chi-nguyen-hong-hai-uy-vien-ban-thuong-vu-tinh-uy-pho-chu-tich-ubnd-tinh-lien-tuc-to-chuc-cac-cuoc-hop-va-co-chi-dao-sat-sao-de-day-nhanh-tien-do-trien-khai-thi-cong-cac-tuyen-cao-toc.jpg
Nguyen Hong Hai, Member of the Provincial Party Standing Committee and Vice Chairman of the Provincial People’s Committee, has continuously convened meetings and issued close, hands-on directives to accelerate the implementation of the expressway projects.

Nguyen Hong Hai, Vice Chairman of the Provincial People’s Committee, has been assigned direct oversight of both projects. During meetings and field inspections, he has required immediate clarification of specific issues: which segments face land clearance obstacles, which dossiers are incomplete, and which stages are delayed—and why.

Issues are not merely recorded but resolved on-site, with clear solutions, responsible units, and strict deadlines—down to specific days or even hours for urgent tasks. This approach creates direct pressure for immediate action.

Meetings have shifted from “report listening” to “problem solving.” Outstanding issues are not deferred but resolved within defined timelines.

Official Notice No. 360/TB-UBND (March 29, 2026) functions not just as a conclusion, but as an implementation directive, assigning clear tasks, deadlines, and accountability.

In working sessions, delayed items are no longer merely noted but are clearly identified in terms of causes, responsibilities, and required remedies within the shortest possible timeframe. Each stage and task is thoroughly dissected, creating constant management pressure that compels agencies to shift from process-based handling to progress-driven execution.

This decisive leadership has generated a strong ripple effect, ensuring that no part of the system remains on the sidelines. Departments, local authorities, and investors are required to accelerate, operate at higher intensity, strengthen coordination, and assume clear accountability for each assigned task.

Công tác rà phá bom mìn đã và đang được các đơn vị nhà đầu tư triển khai thực hiện
Mine clearance operations have been and are being carried out by the project investors.

“Hard Deadlines” to Remove Bottlenecks

Provincial directives have been translated into detailed action plans focusing on legal procedures and technical documentation.

A key breakthrough is the implementation of Resolution No. 407 on converting 104.25 hectares of forest land—previously a major bottleneck. Instead of sequential processing, agencies now work in parallel to shorten timelines.

An inter-agency task force has been established to streamline coordination and reduce repetitive revisions.

The Department of Construction serves as the central coordinator, holding frequent briefings and ensuring immediate resolution of pending issues.

According to Deputy Director Nguyen Thanh Chuong, deadlines are fixed and non-negotiable.

For Tan Phu – Bao Loc:

  • Technical design: before April 20, 2026
  • Investment adjustment: before April 25, 2026
  • Alignment adjustment: before April 21, 2026
  • Forest conversion: before April 20, 2026
  • Bauxite assessment: before April 19, 2026
Trên tuyến cao tốc Bảo Lộc - Liên Khương, các đơn vị nhà thầu bố trí 11 điểm triển khai thi công
Along the Bao Loc – Lien Khuong expressway, contractors have established 11 construction fronts.

For Bao Loc – Lien Khuong:

  • Technical design: before April 25, 2026
  • Forest conversion: before April 16, 2026
  • Bauxite assessment: before April 18, 2026
  • Construction readiness: by April 25, 2026

Beyond task assignment, the Department of Construction is directly involved in resolving bottlenecks during appraisal, handling documentation immediately as issues arise to avoid backlogs. Specialized divisions have been instructed to shorten processing time and work continuously to ensure overall progress.

Project Management Unit No. 1 has been tasked with closely monitoring the progress of each component, while completing the feasibility study report for the technical infrastructure relocation subproject by May 2, 2026—an immediate milestone following the construction kick-off phase.

Ở dự án Bảo Lộc - Liên Khương, tiến độ giải phóng mặt bằng đạt gần 50%, nhưng phần còn lại lại rơi vào các khu vực phức tạp, liên quan đến đất ở, đất sản xuất, hạ tầng dân sinh... cần nhiều thời gian xử lý
For the Bao Loc – Lien Khuong expressway project, contractors have secured about 50% of cleared land for construction, while complex areas involving residential land, production land and civil infrastructure are still being urgently processed by relevant authorities.

The provincial Land Fund Development Center, together with local authorities, is accelerating compensation and site clearance. Bottleneck cases are being reviewed on a household-by-household and site-by-site basis, with a focus on resolving them completely under the principle of “no prolonged backlog.”

Notably, investors and contractors have shifted their approach. Instead of waiting for full conditions across the entire route, they are proactively commencing work at ready sections. This strategy enables earlier activation of construction sites while creating reverse pressure on the remaining preparatory stages.

Tại dự án cao tốc Tân Phú - Bảo Lộc, việc khảo sát địa hình và thủy văn đạt khoảng 90%, nhưng khảo sát địa chất mới đạt khoảng 55%
For the Tan Phu – Bao Loc expressway project, topographic and hydrological surveys have reached approximately 90% completion.

In parallel, inspection and supervision are being carried out continuously. Emerging issues are identified early and addressed immediately, preventing them from evolving into new bottlenecks. As a result, the pace of handling is accelerating day by day, tied to each specific task.

It is evident that the momentum of the two expressway projects is not driven by any single entity, but by the coordinated operation of the entire system. From the provincial to grassroots levels, from management agencies to investors, all stakeholders are working within a unified timeline, where each link is under pressure to deliver on its assigned responsibilities.

Đồng chí Hồ Văn Mười, Ủy viên Ban Chấp hành Trung ương Đảng, Phó Bí thư Tỉnh ủy, Chủ tịch UBND tỉnh Lâm Đồng thăm hỏi, động viên người dân thuộc diện giải phóng mặt bằng vùng dự án cao tốc đi qua
Central Committee Member, Deputy Secretary of the Provincial Party Committee and Chairman of the Lam Dong Provincial People’s Committee Ho Van Muoi visits and encourages residents affected by site clearance for the expressway projects.

Leadership Imprint and Lessons Learned

The defining feature is not just determination, but a shift in approach: tackling issues directly, resolving them thoroughly, assigning clear accountability, and enforcing strict timelines.

Toàn bộ hệ thống chính trị tỉnh Lâm Đồng đang đồng loạt vào cuộc, với quyết tâm tháo gỡ từng điểm nghẽn, đưa dự án tiến về phía trước bằng những giải pháp cụ thể
The entire political system of Lam Dong Province is moving in unison, determined to remove each bottleneck and advance the project through concrete solutions.

Leadership is demonstrated not only through directives but through on-site presence and hands-on coordination.

A practical, task-specific approach to governance has created a unified rhythm across the system, enabling decisions to be translated into action more quickly and effectively.

Mặc dù các dự án đã khởi công, tuy nhiên các đơn vị nhà thầu chưa đủ điều kiện để triển khai thi công ngay trên diện rộng
To date, contractors have secured the necessary conditions to commence large-scale construction across the expressway routes.

Drawing from the implementation of the two expressway projects, a number of important lessons have emerged. Key lessons include:

  • Identifying bottlenecks accurately
  • Enforcing timeline discipline
  • Strengthening inter-agency coordination
  • Enhancing leadership accountability
  • Placing people at the center

Public consensus has become a decisive factor—each square meter of cleared land represents not just progress, but trust.

Các đơn vị thi công đang khẩn trương làm đường phục vụ triển khai đồng loạt các mũi thi công trên 2 tuyến cao tốc
Construction units are urgently building access roads to facilitate the simultaneous deployment of multiple construction fronts on the two expressway routes.

A new governance approach is emerging: clear accountability, parallel processing, strict timelines, and action-oriented leadership.

These lessons not only help accelerate current expressway projects but also lay the foundation for future infrastructure, urban, agricultural, and tourism development.

2 tuyến cao tốc Tân Phú - Bảo Lộc và Bảo Lộc Liên Khương khi hoàn thành và đưa vào sử dụng sẽ mở ra không gian kết nối mới cho tỉnh Lâm Đồng nói riêng và khu vực Tây Nguyên nói chung
Once completed and put into operation, the Tan Phu – Bao Loc and Bao Loc – Lien Khuong expressways will open up a new connectivity space for Lam Dong Province in particular and the Central Highlands region as a whole.

As governance methods evolve, responsibilities become clearer, and public trust strengthens, these expressways will not only enhance connectivity but also shape a more proactive, flexible, and sustainable development model.

Ultimately, their greatest value lies not only in the kilometers of road built, but also in how the entire system has transformed determination into tangible results—propelling Lam Dong forward in a new phase of development.

Read more

Highlight

    Latest news
    Episode 3: When the Entire Political System Moves in Unison
    • Default
    POWERED BY ONECMS - A PRODUCT OF NEKO