News

National Highway 28B Set for Completion in April 2026

Minh Chuong - Lam Khoa 16/04/2026 08:17

Favorable weather and progress in site clearance have created favorable conditions for the National Highway 28B upgrade and rehabilitation project. The project investor has pledged to speed up construction, targeting completion of asphalt paving along the entire route by the end of April 2026, in line with directives from the Lam Dong Provincial People’s Committee.

thi-cong-nuoc-rut-de-ve-dich(1).jpg
The National Highway 28B upgrade and rehabilitation project is being accelerated toward completion.

Site Clearance Completed, Construction Gains Momentum

In recent days, as the initial section of National Highway 28B connecting to National Highway 1A—passing through Luong Son Commune—has been largely handed over, contractors have mobilized manpower, equipment, and machinery to speed up construction.

To ensure overall progress, the entire political system of Luong Son Commune has worked intensively, day and night, to mobilize residents to hand over land.

To date, among 320 cases subject to land clearance with approved compensation plans, the majority of residents have agreed to receive compensation and hand over land for the project.

xa-luong-son-tich-cuc-van-dong-nguoi-dan-ban-giao-mat-bang-phuc-vu-du-an(1).jpg
Luong Son Commune is actively mobilizing residents to hand over land for the project.

Le Dang Phap, Vice Chairman of the Luong Son Commune People’s Committee, said that local authorities have actively coordinated with the Vietnam Fatherland Front Committee to promote public awareness and mobilize residents to accept compensation and hand over land. Currently, only two households, covering approximately 15 meters, have yet to comply.

We are continuing to persuade the remaining households to hand over their land and expect to complete site clearance by the end of this week. At the same time, all necessary documentation has been prepared to enforce compulsory measures in accordance with regulations for cases that fail to comply.

Le Dang Phap, Vice Chairman of the Luong Son Commune People’s Committee, Lam Dong Province

At present, site clearance for the National Highway 28B project has been largely completed, ensuring uninterrupted construction.

anh-nguyen-minh-truong-da-som-ban-giao-36m-mat-tien-duong-phuc-vu-thi-cong-du-an(1).jpg
Nguyen Minh Truong, a resident of Luong Son Commune, has early handed over 36 meters of roadside frontage to support the project’s construction.

Strong Direction to Ensure Timely Completion

During an on-site inspection of the project on March 11, 2026, Ho Van Muoi, Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, and Chairman of the Lam Dong Provincial People’s Committee, emphasized that National Highway 28B is a critical driver of the province’s development, especially while Lien Khuong Airport remains temporarily closed.

Chủ tịch UBND tỉnh Lâm Đồng Hồ Văn Mười yêu cầu đẩy nhanh tiến độ thi công Dự án Cải tạo, nâng cấp Quốc lộ 28B (ảnh Nguyễn Lương)
Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, and Chairman of the Lam Dong Provincial People’s Committee Ho Van Muoi calls for the completion of the National Highway 28B upgrade and rehabilitation project within April 2026 (Photo: Nguyen Luong).

He requested the Central Road Project Management Board to act decisively, mobilizing maximum manpower and equipment, and increasing work shifts to ensure completion by the end of April 2026.

Regarding overall progress, 61 out of 68 km of the route have been asphalted. The remaining 7 km, spread across several sections near the start of the route, are currently being fast-tracked.

muc-tieu-tham-nhua-toan-mat-duong-ql28b-trong-thang-4-2026(1).jpg
The goal is to complete asphalt paving across the entire National Highway 28B within April 2026.

Weather conditions are currently very favorable, and site clearance has been largely completed. We are organizing rolling construction across sections and commit to completing asphalt paving of the entire roadway by April 30.

Chu Minh Thuan, project executive from the Project Management Board.

nut-giao-ql28b-voi-cao-toc-vinh-hao-phan-thiet(1).png
The interchange between National Highway 28B and the Vinh Hao – Phan Thiet Expressway.

At present, the section from the Vinh Hao – Phan Thiet Expressway interchange to National Highway 20 has been fully paved, allowing traffic to flow smoothly. This route is increasingly becoming a preferred choice for residents and tourists traveling to Da Lat.

Read more

Highlight

    Latest news
    National Highway 28B Set for Completion in April 2026
    • Default
    POWERED BY ONECMS - A PRODUCT OF NEKO